Been a while since a posting -sorry about that, was away. Crews have completed metal panel installation on both sides of ABC and are now moving to install on the streetsides of DE, FG and HJK. They will probably be done in less than two weeks.

Crews are also following behind and installing caulk. They have 2 or 3 weeks left as well.

We are almost done with the CAPSUR wash on the courtyard balconies and have several to do on the streetside. I'm waiting for all test results to be returned, but will post those that need to be cleaned and those that can be used again (but for now, bear with us while we continue cleaning).

The soil excavation plans are coming together. We have to take soils from in front of ABC, DE and FG, and are trying to figure out the best way to get them out without creating unneccessary hassles. Also have to take soils from streetside units almost all the way around.

As soon as these plans are final we'll post. We're open to another community meeting if anyone wants to discuss how this will play out.

Thanks as always and feel free to stop by or call if you have questions or concerns.

Richard