Monday, November 3, 2008

Monday 11/3 Update

The metal work has been completed. Sorry about the drilling into the building, but this had to happen. Crews are applying final caulk on the streetside of buildings FG and then will complete unit HJK.

Crews are also completing final touchup and paint overspray cleaning, and will be sweeping and wiping down balconies and window sills.

The only remaining work is the CAPSUR chemical wash on select balconies and the soil excavation work planned for areas in the courtyard and on the streetside.

Since we are taking soil from the courtyard and will be using large excavating machines to do so, we will be restricting access to half of the courtyard during this operation. This will be a larger area than we have taken in the past, but it is necessary to ensure a complete separation between children and these large machines. We'll send a PDF plan of the area shortly.

There will be concrete chip sampling required after we complete the CAPSUR wash on the balconies. This is to ensure the completeness of the cleaning process. It's noisy, but relatively short in duration.

As always, feel free to email or call with any questions or concerns.