Friday, October 3, 2008

Friday 10/3 Update

I apologize for the lack of updates. We've been busy and it just slipped.

Crews have completed all caulk removal activities on the entire project. They've also completed all painting in the courtyard of all units. We are now in a race to complete the metal panel installation on courtyard ABC, the replacement of caulk on courtyard units FG, DE and ABC, and the re-mobilization to the streetside to paint the brick work and install the same metal and caulk before the weather turns any worse.

We should have the poly sheeting off of units ABC by today, but certainly by end of the day Monday. The crews are on the streetside units installing and painting starting with HJK and will be moving around the complex from HJK to FG, to DE, and then ending with ABC.

Since we're not covering your windows for this phase we may push any open windows closed while we are close to a unit to minimize paint fumes. We've been leaving the fans on now that the caulk removal phase is over as the moisture and mold issues were causing bigger problems.

We are still accessing balconies for testing, cleaning and caulk replacement. There will be times when we will tape your windows closed to apply certain cleaning agents, but will not be installing poly.

I'll try to post another note shortly.

Richard