Monday, November 3, 2008

CAPSUR Wash and Concrete Samples

Based on sampling analysis, crews will be performing CAPSUR wash on the following streetside balconies: A1, A5, B1, B2, B4, B5, B6, D5, E2, E4, F5, G4, G6, H1, J1, J3, and J4, starting 11/3 (if the weather permits).

We've already performed CAPSUR wash on the following courtyard balconies: C4, C5, C6, D1, D2, D4, E2, E3, E5, H1 and H2.

Concrete chip samples will need to be taken on all of the above balconies post-wash to ensure accuracy and completeness of procedure.

We also washed and sampled F1, F2, F3, F4 G1, G4 and G5 on the courtyard side. These failed post-wash tests and may be re-cleaned and re-sampled, but a decision on this is pending.

As soon as we have information on the progress we'll post any updates. Thanks.

No comments: