Friday, August 15, 2008

Update Friday 8/15

Work is progressing on streetside HJK. Caulk replacement is complete on several units and we are still scheduled to begin prep and plastic install on the courtyard side of HJK on Monday.

Paint on FG is moving forward as well and if we can get the weather to cooperate we might be able to remove plastic from the streetside of FG by the end of next week.

We are going to try and leave a 'window' or opening in the plastic on the large plate glass windows on each unit going forward so that you'll have views and a bit more light. As we bring machines into the courtyard and install fence we will need to block door access as well during the week. We plan on being as flexible as possible but restricted access to these doors during the week is likely.

Remember that we need to have balcony materials (on HJK) removed by Monday morning before the crews start.

Thanks as always.