Tuesday, August 26, 2008

8/26 Update

Work continues on all streetside units and courtyard HJK. We've completed, or nearly completed paint application on DE and will begin spray application on streetside ABC this week.

We are also collecting concrete 'chip' samples from the side of ABC today so it will be a bit noisy for a short period.

We've had a number of concerns about the fumes and exhaust odors in the apartments. We're considering a number of alternatives to minimize this, but as the joints are open during paint application, and are also open while the new caulk is being installed, odors from both products will likely continue to migrate into the units - even though the house fans have been shut down.

If possible, keeping your windows closed will help. The outside temps haven't made this particularly attractive and for those units (HJK) where we are still installing caulk on the opposite side this is almost impossible. We will minimize this approach going forward.

Please feel free to call or email anytime. If you have any suggestions on ways we can make this easier we're open to it.

Thanks.

1 comment:

Heather said...

The caulking removal began on our apartment playground-side yesterday, and since they finished we have strange smell in our livging room and kitchen. Is something applied at this stage of the project too?