Friday 9/5 Update

Caulk removal has started on courtyard FG and paint application is continuing on courtyard HJK.

We've heard from several that the paint fumes in the apartments, while strong during the day, dissipate for the most part in the evening. We're still turning the house fans off during the day and restarting them at night, so hopefully this is helping.

We will be able to open all entrances, other than the courtyard doorways into unit FG, this weekend. Sorry to everyone in FG, but the crews have just started on those units and the loose caulk and other materials will still be too close to the entryways to allow safe passage this weekend.

We appreciate everyone's patience and understanding. I can always be reached at 978-390-6915 or rgang@mit.edu, or at the trailer.

Thanks, and have a great weekend.