Thursday, September 4, 2008

9/4 Update

Encapsulation paint has started on the courtyard side of HJK and caulk removal has started on the courtyard side of FG. Crews will be collecting concrete chip samples from the sides courtyard sides of FG Friday, the 5th - this will be noisy, but will only last a short while and will not begin before 10 AM.

Crews will begin covering windows and doors on the courtyard side of F tomorrow, and caulk removal wil continue on FG into early next week.