We've discussed taking a large area of the courtyard as the large equipment is dangerous and difficult for operators to see on all sides. This taking will only be during the working day and we will open the fences in the evening and weekends to allow access.
We've also posted signage designating two spaces on Audrey Street and four spaces at the entrance to Amherst Alley (between units F and H) for clearance to deliver and remove roll-off containers being used to transport soils.
Building cleaning will continue for a few more days, but this work is almost complete as well.
Thanks.
Richard